Cowell Community Waste Management Scheme
Duration: February 2015 – July 2016
Client: District Council of Franklin Harbour
Location: Cowell, South Australia
Project Value: $7.5 million
Project Description:
The Cowell - Community Waste Management Scheme (CWMS) was constructed by Baker Civil Australia Ptd Ltd, under its former name Baker & Gibbons Pty Ltd and included the supply and install of all components of a CWMS. Components constructed for the Cowell CWMS included:
13,500m; PVC Gravity Sewer Mains, dia. 150 – 200mm
Associated Precast Concrete Manholes & PVC Maintenance shafts
7,000m; PVC & PE100 Sewer Rising Mains, dia. 50 - 200mm
3,500m; PVC Recycled Water Main, dia. 150mm
4x Pre-Cast Sewer Pump Station (SPS) Packages
Challenges:
Involved in the construction of the Cowell CWMS were a range of challenges that needed to be overcome in order to construct the varies components. Some were more significant than others but all needed to be overcome in order to complete the project. They included:
Hard rock over 70% of the area of the township of Cowell where the project was to be constructed
Deep trench excavation up to 5m
60x Independent allotment pumped house connection packages
The layer of rock encountered over the majority of the township was overcome with Baker Civil’s capability to increase its operating capacity to the requirements of the job by purchasing a Vermeer T755 rock trencher. This machined allowed the rock to be easily handled providing an efficient method of excavation, minimizing damage to roads from break outs if the rock was otherwise excavated with rock breakers and excavators, the spoil was sufficiently milled to be reused as backfill material on the gravity drain trenches and minimized machine hours. Deep excavations were handled with our company owned trench shields and benching. Baker Civil has extensive experience to draw on from a technical stand point, being able to find alternate design options for alignments and catchment areas. In the case of the Cowell CWMS eliminating an SPS and approximately 55 of the independent pumped connections. This was a cost effective solution because it minimized ongoing running costs and was overall cheaper to install.
Final Outcome:
The Cowell CWMS was completed on time within the 18 months allowed and within budget.